Conservation Minutes, January 10, 2006
HANSON CONSERVATION COMMISSION
MINUTES OF THE PUBLIC MEETING OF JANUARY 10TH, 2006
HANSON TOWN HALL, LIBERTY ST., HANSON, MA


Called to Order at 7:30 PM under M.G.L. Chapter 131, s.40 and the Hanson By-Law 1-13, s.5. by Philip Lindquist, Chairman, in the Conservation Office at the Town Hall.

Members Present:           Philip R. Lindquist, Chairman        
  Sean Chrisman, Member
                           David Harris, Member
                           Ron Grattan, Vice Chairman
Members Absent:    None
Others Present:            Rebecca Nehiley, Secretary
  Janine Delaney, Agent


Approval of Minutes:   
        
Motion to approve Minutes of November 22nd, 2005:  David Harris
Second:  Sean Chrisman
Vote:  3-0-1 (Ron Grattan abstaining)

Motion to approve Minutes of December 9th, 2005:  Dave Harris
Second:  Sean Chrisman
Vote:  4-0-0

Motion to approve Minutes of December 20th, 2005:  Dave Harris
Second:  Ron Grattan
Vote:  3-0-1 (Sean Chrisman abstaining)


Appointment

7:30 PM Appointment with Peter Dillon of The Chilmark Company to discuss a water main replacement on Main Street for Brookside II.

Ms. Delaney made comments regarding the difficulty.  It initiated when the contractors unknowingly used a plan that had an inaccurate wetland line while installing a water main on Main Street for a new subdivision.  Consequently, the work that they performed was in the buffer zone within 30’ of a wetland.  As mitigation, Mr. Dillon submitted a letter from Chilmark offering in writing to install a silt fence, clean out the accumulated sediment, trash, etc. and loam and seed the slope in the spring.  Ms. Delaney recommended approval for work to commence under the previous filing.  (DEP #SE175-441)

        Motion to approve the mitigation plan under previous Order of Conditions:  Dave Harris
        Second:  Ron Grattan
        Vote:  4-0-0

HANSON CONSERVATION COMMISSION
MINUTES OF THE PUBLIC MEETING OF JANUARY 10TH, 2006
HANSON TOWN HALL, LIBERTY ST., HANSON, MA
Page 2


Public Hearings

7:45 PM  Notice of Intent for the construction of a 16’x32’ addition and a 12’x20’ sunroom
and a septic system upgrade at 52 Richard Road, Assessors Map 80, Lot 54 for Paul Anderson represented by Ross Engineering Co., 683 Main St., Norwell, MA  (New Hearing)  (DEP #175-0486)

David Harris read the Public Hearing Notice and the abutters were verified.  Greg Tansey of Ross Engineering presented a revised plan and made the presentation.   The proposal calls for the removal of the existing leaching field adjacent to the wetland and the installation of a new jet system treatment plant approved by the Board of Health in a further location on the lot.  The proposal also calls for the construction of an addition and a sunroom.   Ms. Delaney commented that the addition would not meet the 50-foot no build setback requirement.  However, since the house was built in 1969 and the applicant was asking for a hardship, Ms. Delaney suggested that the Commission approve the variance request in anticipation of mitigation in the form of drywells and plantings along the wetland line to be shown on the as-built.

Motion to approve a variance to build within the 50-foot buffer zone and issue an Order of Conditions with special conditions:  Ron Grattan
        Second:  Dave Harris
        Vote:  4-0-0    


8:00 PM Continued  Request to Amend an Order of Conditions to allow a modification to relocate garages at 255 Rear Liberty Street, Assessors Map 82, Lot 6-1 for Dennis Leary, Trustee for Hudson Park Associates, N.T., 2 Columbia Rd., Pembroke, MA  02359   (DEP #175-0433)  - Continued to January 24th at 8:15 PM per request of applicant


8:15 PM Appointment with Bob Gosselin of GosCon represented by Grady Engineering to discuss Certificate of Compliance requests for Litchfield Lane and Proudfoot Way.

Kevin Grady of Grady Engineering attended the meeting relating to the four (4) Certificate of Compliance Requests made for Litchfield Lane and Proudfoot Way by the developer, Bob Gosselin.  A lot of correspondence had transpired between the agent and Mr. Gosselin/Grady Engineering over the last several months with regard to unresolved conditions at each of the properties.  Ms. Delaney pointed out that although there was an extensive file and a record of the hearings with Mr. Gosselin, an Order of Conditions was never issued for the subdivision itself.  Mr. Grady suggested that Mr. Gosselin had made a good faith effort to rectify the issues as per conversations with the Conservation Commission.  The meeting resulted in the following decisions per each COC Request:



HANSON CONSERVATION COMMISSION
MINUTES OF THE PUBLIC MEETING OF JANUARY 10TH, 2006
HANSON TOWN HALL, LIBERTY ST., HANSON, MA
Page 3


100 Litchfield Lane, Lot 8 (DEP #175-409) – Mr. Grady said that the permanent setback markers had been installed as required, but the silt fence had not been removed.  The owners, Tom and Nancy Rogers attended the meeting and voiced their frustration over the detention basin on their lot that they feel doesn’t drain properly.  Also, their haybales and silt fence were not removed and are unsightly.  Ms. Delaney wanted a corrected as-built to show all relevant structures on the plan.  Mr. Lindquist said that the Planning Board was working with Mr. Gosselin to work out the detention basin issues.  The Commission denied a Certificate Compliance Request at this time.

92 Litchfield Lane, Lot 7 (DEP #175-391) – Mr. Grady said the permanent setback markers had been installed and the silt fence was removed.  Ms. Nehiley had received a phone call from the owners, the Wynne’s, who were satisfied that all had been completed.

        Motion to issue a Certificate of Compliance:  Dave Harris
        Second:  Ron Grattan
        Vote:  4-0-0

19 Proudfoot Way, Lot 5 (DEP #175-387) -  Mr. Grady said that Mr. Gosselin is seeking relief from the placement of permanent setback markers in three locations.   Ms. Delaney stated that the driveway had encroached into the 50-foot no-disturb setback, which was more of a reason to install markers for future reference. This Request was also denied.

5 Proudfoot Way, Lot 6 (DEP #175-410) – Ms. Delaney had asked for and not yet received a revised plan that shows a stone wall that was installed instead of rip-rap.   Certificate of Compliance denied pending revised as-built.

Mr. Grady was asked to advise Mr. Gosselin of the ongoing issues, and notify the Commission when all that was discussed at the meeting is completed and a final inspection will be conducted.  Also, the Commission deemed that additional site visit fees shall be assessed.

8:30 PM  Continued Notice of Intent for a revised proposal for the construction of eight (8) single-bedroom condominium units with parking and septic within 100 feet of a bordering vegetated wetland at 1139 Main St., Assessor’s Map 43, Lots 36A & B and 36.  A portion of the construction falls within the 100-foot inner riparian zone. Proposal includes clean up of existing construction debris and soils on Lot 36.   Applicant:   Demco Enterprises, Inc., 31 Perkins Street, Bridgewater, MA  02324 represented by Land Planning, Inc.. (DEP #175-0460) – to be continued to an unspecified date after ZBA hearing per request of Bob Crowell of Land Planning, Inc..

Discussions

Letter (11/21/05) from Mary Mahoney, Project Manager for WHRHS project re:  Botanist Mitigation report- The Commission received an update from Sharon LePorte, botanist for the restoration at the wetland crossing which is still under review.  
HANSON CONSERVATION COMMISSION
MINUTES OF THE PUBLIC MEETING OF JANUARY 10TH, 2006
HANSON TOWN HALL, LIBERTY ST., HANSON, MA
Page 4

Letter (11/25/05) from Northeast Contractors, Inc. regarding response to ConCom Request - reviewed
Letter (11/28/05) from John McEwan regarding Extension Request for WHRHS project (DEP #SE175-388)

Motion to approve Extension of Order of Conditions for two years from date of issue:  Dave Harris               Second:  Ron Grattan    Vote:  4-0-0

Two (2) Letters dated (12/03/05) from Marcionda & Associates regarding erosion control & E.O. at Stonebridge Commons (DEP #SE175-396) - reviewed
Letter (12/12/05) from Marchionda & Associates regarding Wildlife Habitat Enhancement area at
Stonebridge Commons (DEP #SE175-396) - reviewed
Steve Nicoletta dewatering plans – The Commission asked Ms. Delaney to send a letter requesting that Mr. Nicoletta submit a detailed plan dated and stamped by an Engineer.
Letter (12/8/05) from Chris Pongratz regarding the easement and access road at 22 Industrial Blvd. – This was determined to be a Water Department issue.
Lot 1, Pleasant Street (DEP #SE175-0456)  - Ms. Delaney approved of revised plan and advised Commission.
Pinehill Estatesreviewed
72 Kings Landing (11/30/05)reviewed
Hanson Trails Committee – dedication scheduled for June 6, 2006
Town Reportreviewed, okay to send to Merry
Conservation Commission Rules & Regulations – Ms. Nehiley found an office copy of the By-law and Rules and Regulations that definitively showed the 50-foot no disturb regulation effective as of July 30, 1990.


Enforcement Issues

261 Maquan Street – stockpiling of woodchips in wetland, Ms. Delaney will send letter
889 Winter Street –  haybales eroded, Ms. Delaney will send letter

WHRHS – Enforcement Order/penalties, Stonebridge Commons/penalties, 78 Forest Trail/ Enforcement Order/penalties

Above mentioned properties were discussed.  The Commission decided to issue penalties to accompany the Enforcement Orders previously issued.  The maximum fine is $300.00 per day per violation.  At this time, the Commission determined to send a total of a $300.00 fine to each contractor for all of the violations at each site.

Administrative Issues

Payroll - signed


HANSON CONSERVATION COMMISSION
MINUTES OF THE PUBLIC MEETING OF JANUARY 10TH, 2006
HANSON TOWN HALL, LIBERTY ST., HANSON, MA
Page 5

Cell phone use re-imbursement

        Motion to reimburse Janine Delaney for cell phone use at $25.00/month:  Dave Harris
        Second:  Sean Chrisman
        Vote:  4-0-0

Meeting Day- The Commission decided to leave the schedule as is on the second and fourth Tuesday of the month.


Certificate of Compliance

Request for Certificate of Compliance for 800 Franklin St., Map , Lot for Dale Southworth  (DEP #SE175-289) – ongoing issues, continued


Adjournment

        Motion to adjourn at 10:05 PM:  Sean Chrisman
Second:  David Harris
Vote:  4-0-0